RR.A.SD02.UPS-B

Scheduled Maintenance Report for Tornado Datacenter GmbH & Co. KG

Completed

The scheduled maintenance has been completed.
Posted Jan 14, 2025 - 13:00 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 14, 2025 - 12:00 UTC

Scheduled

We'll be changing the external Bypass Switch of RR.A.SD02.UPS-B, providing supply to B-Feed of RR.A.R03 as well as RR.A.R04 cabinet rows on distribution SD02. During the maintenance, the feed will be without electrical supply from the mains distribution, which means that the feed on those cabinets will be without power during the maintenance window, which can last up to 60 minutes.

We urge all customers to ensure redundant connection or reconnection of single PSU equipment on the other feed, as well as using proper STS/ATS measures to implement redundancy on the customer level side.
Posted Oct 25, 2024 - 21:42 UTC
This scheduled maintenance affected: Uninterruptible Power.