Public Grid Power Connection - Capacity Upgrade

Scheduled for Nov 22, 08:00 - 11:00 UTC

Scheduled

We will be carrying out a upgrade of the public grid power connection in order to increase the available power capacity available to Tornado Datacenter. During the upgrade, the low voltage mains switch board of the building as well as the public grid power connection will be increased in it's capacity. We will operate the datacenter on generator power during this time. No impact to customers is expected, the UPSes will take over the load during switching operations, during the works, the load will be provided by generator power.
Posted Oct 29, 2025 - 10:58 UTC
This scheduled maintenance affects: Public Grid Power Supply.