During the specified week, a certified pipeline construction contractor will implement our new chilled water circulation loop, expanding the available cooling capacity based on our MTA Aries chiller platform.
The scope of work includes welding activities within the future Room B area. Minor visible construction activity in this area may be noticeable during the implementation phase. All works will be carried out during normal datacenter operations.
Room B is physically separated from the active Room A environment and is not connected to the live airflow system. The construction zone is fully isolated from production space. As a result, no air pollution, particulate contamination, or air quality impact to active infrastructure will occur.
Throughout the implementation period, our existing DX air conditioning systems operate with sufficient reserve capacity to fully maintain thermal stability (temperature and humidity) within defined operational thresholds. The chilled water expansion is therefore performed without reliance on temporary cooling measures or operational constraints.
Following mechanical completion and commissioning, the new chilled water circulation loop will be taken live in April 2026, further increasing overall cooling resilience and capacity.
Environmental parameters - including temperature, humidity, and air quality - are continuously monitored to ensure stable operating conditions at all times.
No service interruption or operational impact is anticipated.
Posted on
Mar 03, 2026 - 21:15 UTC
We will be disconnecting Tornado Datacenter from public power grid in order to carry out a test of the emergency generator under load.
Posted on
Oct 21, 2025 - 13:24 UTC
We will be disconnecting Tornado Datacenter from public power grid in order to carry out a test of the emergency generator under load.
Posted on
Oct 21, 2025 - 13:25 UTC
We will be disconnecting Tornado Datacenter from public power grid in order to carry out a test of the emergency generator under load.
Posted on
Oct 21, 2025 - 13:25 UTC